Plan of the Day: October 7th
Dirtworks will be pavement patching on 9 Mile Rd between Campbell Rd and Otten Rd. They will also be working on field entrance culverts on Finney Rd.
Plan of the Day: October 6th
Dirtworks will be pavement patching on 9 Mile Rd between Campbell Rd and Otten Rd. They will also be working on field entrance culverts on Finney Rd.
Plan of the Day: October 4th
There will be no work on public roads this weekend.
Plan of the Day: October 3rd
Dirtworks will be installing field entrance culverts and aggregate surface on 9 Mile Rd. Traffic control will have advanced warning signs with flagmen.
Plan of the Day: October 2nd
Dirtworks will be installing field entrance culverts on 9 Mile Rd between Peach Rd and IL Rt 111. Traffic control will have advanced warning signs with flagmen.
Plan of the Day: October 1st
Dirtworks will be installing field entrance culverts on 9 Mile Rd. Traffic control will have advanced warning signs with flagmen.
Plan of the Day: September 30th
Dirtworks will be installing field entrance culverts on 9 Mile Rd. Traffic control will have advanced warning signs with flagmen.
Plan of the Day: September 29th
Dirtworks will be installing field entrance culverts on 9 Mile Rd. Traffic control will have advanced warning signs with flagmen.
Plan of the Day: September 26th
Dirtworks will be installing field entrance culverts and ditch grading on 9 Mile Rd. Traffic control will have advanced warning signs with flagmen.
Plan of the Day: September 25th
Dirtworks will be installing field entrance culverts and ditch grading on 9 Mile Rd. Traffic control will have advanced warning signs with flagmen.