Plan of the Day: September 3rd
Dirtworks will be installing field entrance culverts and aggregate surface in North Otter Township. Traffic control will be advanced signing with flagmen.
Plan of the Day: September 2nd
Dirtworks will be installing field entrance culverts in North Palmyra Township. Traffic control will be advanced signing with flagmen.
Plan of the Day: August 29th
Dirt works will be installing field entrance culverts in North Palmyra Township. Traffic control will be advanced signing with flagmen.
Plan of the Day: August 28th
Dirtworks will be installing field entrance culverts in North Otter Township. Traffic control will be advanced signing and flagmen.
Plan of the Day: August 27th
Dirtworks will be installing field entrance culverts in North Otter Township. Traffic control will be advanced signing and flagmen.
Plan of the Day: August 26th
Dirtworks will be placing the top lift of HMA Shoulders on IL Rt. 267 (SBL) approximately 0.25 miles north of Scottville Rd. Traffic will be restricted to one lane with flagmen. Blotting roads will continue as needed.
Plan of the day August 25th
Dirtworks will be removing and replacing HMA shoulers on IL Rt 267 approximately 0.25 miles north of the Scottville Rd intersection. Traffic will be restricted to one lane with flagmen. Blotting roads will continue as needed.
Plan of the Day: August 23rd
There will be no work on public roads this weekend.
Plan of the Day: August 22nd
Dirtworks will be off loading entrance culvert pipe and blotting roads as needed.
Plan of the Day: August 21st
Dirtworks will continue to work on SWPP maintenance items and blot roads as needed.