Next week the cement stabilization of the roadways will commence. Road closures will be up to seven (7) days to allow cement stabilization to cure.
The following roads will be closed and should reopen at the end of the day:
- Finney Rd from Davis Rd to Greenland Rd
- There are no residents living along this road
- The road will be closed for work on culvert C206
- Greenland Rd from Finney Rd to Williamson Rd
- There are no residents living along this road
- The road will be closed for work on culvert C200
- Drake Rd from Finney Rd to Neff Rd
- Residents will have access from the south
- The road will be closed for work on culvert C38
- Bob White Rd from Scottville Rd to Phillies Rd
- There are no residents living along this road
- The road will be closed for aggregate capping
- Davis Rd from Magee Rd to 9 Mile Rd
- Residents living along this road will have access from the north
- The road will be closed for pre pulverization
- Bob's Rd from 9 Mile Rd to the county line
- Residents living along this road will have access from the north
- The road will be closed for aggregate surface over culverts
- Ruthland Rd from Trigger Rd to Bob's Rd
- There are no residents living along this road
- The road will be closed for roadway preparation
- Trigger Rd from IL Rt 111 to Ruthland Rd
- There are no residents living along this road
- The road will be closed for aggregate surface over culverts